Friday 10 June 2016

Importance of curing in building construction


 Importance of curing in building construction


In concrete construction, the importance of curing cannot be over-emphasized. Concrete which is not adequately cured and loaded before it attains full strength is very likely to develop cracks. The cracks in concrete adversely affect its durability by corrosion of reinforcement.

IS 456-2000 (plain and reinforced concrete – code of practice) defines curing as “the process of preventing the loss of moisture from the concrete while maintaining a satisfactory temperature regime.” The moisture loss takes place in two ways.  One is by evaporation caused by the heat generated during hydration of cement. Second is by evaporation aided by atmospheric temperature and wind. The evaporation caused by wind and atmospheric temperature increases when the exposed surface area of concrete increases. 

In the case of horizontal  surface such as top of flat slabs, moisture loss is prevented by ponding – making a pond 8 cm to 10 cm deep and keeping it filled with water. If the surface is sloped or vertical, ponding is not possible.  Such surfaces are covered by a layer of sacking, canvas, hessian or similar materials and kept constantly wet. IS 456-2000 stipulates that exposed surfaces shall be kept constantly wet at least for seven days if ordinary Portland cement is used, and at least for 10 days, where mineral admixtures or blended cement are used.

IS 456-2000 permits removal of vertical form-work of column, beams and walls after a lapse of 24 hours of placing concrete. It also permits removal of formwork from the underside of slabs after three days if propos (vertical supports) are re-fixed immediately.  Removal of formwork from the underside of slabs exposes the entire surface to atmosphere and abets moisture loss.  This part cannot be kept wet by ponding or by covering with sacking or hessian.  Spraying of water is also not effective to keep the surface constantly wet. Thus, removal of formwork conforming to provisions of IS code makes it virtually impossible to comply with the provision regarding continuous curing of exposed surfaces for seven or 10 days.

To speed up construction, the columns above the slab are raised the very next day of casting the slab.  When column raising and shuttering for the upper slab are in progress, the ponding of the top surface of the slab is often neglected as it inconveniences the workers engaged in formwork erection.  The ultimate result is inadequate curing adversely affecting the strength and durability of concrete.

Now-a-days, there is a craze for shorter cycle time for slab casting.  The cycle time is the interval between casting one slab and the slab immediately above it. A 10-day cycle time means once the slab at a particular level is cast, the slab immediately above it will be cast within 10 days.  The concrete attains design strength in 28 days. Within that period, two upper slabs will be cast if the cycle time is 10 days.  Formwork blow the lower slab will have been removed, because IS code permits removal of vertical support below the slab (spanning upto 4.5 metre) after a lapse of seven days.  The stipulation that forms shall not be released until the concrete has achieved a strength of at least twice the stress to which concrete may be subjected to at the time of removal of formwork is conveniently overlooked.  Thus, a 10-day-old slab, which, in all probability is not properly cured, carries the weight of the slab immediately above it. It is also subjected to impact load caused by the vibration of concrete and movement of trolleys carrying concrete.

For More...........:




No comments:

Post a Comment